UPDATE 12/03/25:

  • Pleasant St Detour installation is currently scheduled to begin on 01/05/2026.
  • New traffic patterns in place as work begins on phase 2 of construction.
  • Work on stormwater system continues.

 

UPDATE 10/29/25:

  • Work on stormwater system continues.
  • Milling & paving sections of asphalt to begin in November.
  • New road striping to be installed following paving.

 

UPDATE 10/13/25:

  • Crews will be performing digging and grading work for various entrances & curbs.
  • Sidewalks, curbs, and ADA ramps to be installed from car wash entrance to Green Chimney Court.
  • Roadway striping changes currently underway.