Map: Parcels to be developed into future park along W Vaughan Road.

map of N Ashland Park location

 

Step 1: Community Visioning

Please answer a few questions below on what you'd like to see at this future park!

Question title

What is your vision for North Ashland Park? Click the options to rank the following elements from 1st to 4th to show your priorities.

photos of use examples

Question title

What park amenities and elements would you prioritize in the development of North Ashland Park? Select your top 5 choices.

examples of amenities
Click to view results

Question title

What types of programs would you like to see at North Ashland Park?

examples of programs
Click to view results

Question title

How often do you visit a park in the Town of Ashland?

Click to view results

Question title

Which Ashland park or trail do you visit most frequently?

Click to view results

Question title

Sharing your nearest cross-streets helps us tie feedback to location to ensure we hear from all parts of the community.

Question title

Providing your contact information helps us connect your feedback with future updates so your voice continues to shape the conversation.

live
live
Community Visioning (Oct-Dec 2025)

Goal: Gather broad community input on priorities for this future park.

Town staff and Parks & Rec Committee solicits feedback via online survey and in-person pop-ups at events. Phase concludes with publication of Community Input Summary Report.

planned
planned
Concept Development (Jan-Apr 2026)

Goal: Translate community visioning feedback into design criteria.

Parks & Rec Committee reviews Community Input Summary Report and works with Town staff to issue a Request for Proposal (RFP) for conceptual designs.

planned
planned
Design Review & Budgeting (Summer-Fall 2026)

Goal: Review RFPs, gather community input on design proposals, and finalize budget.

Gather community feedback via open house meetings, focus groups, and online input. Parks & Rec Committee reviews all feedback and finalizes design recommendation. Town staff prepares budget for incorporation in FY28 budget.

planned
planned
Construction Begins (July 2027)

Pending FY28 budget allocation and/or additional funding (grants, etc.) secured.