South Taylor Street Park Revitalization

South Taylor Street Park Revitalization

The Town of Ashland is revitalizing South Taylor Street Park to create a more accessible, active, and inclusive community space. Guided by the 2024 concept plan developed with the Timmons Group, the redesigned park will feature a new basketball/futsal court, expanded walking loops, interactive play areas, and improved landscaping. Key amenities include a new parking area, inclusive play equipment, a state-of-the-art high school sized basketball and futsal court, and an ADA accessible walking loop. The playground, installed in 2022, and picnic shelter will remain.

Construction is being completed by Talley & Armstrong, with work expected to be finished by winter 2026. Once complete, the updated park will offer a vibrant mix of recreation, play, and gathering opportunities for residents of all ages. Currently, the park is open, but visitors are asked not to enter the fenced in areas.

concept plan for the park

Step 1

UPDATE 07/31/26:
Playground refresh is complete. The basketball court and new pathways have been poured. Resurfacing of the basketball court, painting, and installation of hoops is expected in the coming weeks. We're getting close!

 

S Taylor Playground

 

S Taylor pathways

 

UPDATE 04/13/26:
With the winter weather behind us, crews have resumed clearing the site and begun pouring concrete for the walking path. Construction on the basketball court should begin in the next few weeks.

s taylor 1

 

s taylor 2

 

UPDATE 12/03/25:

Crews continue clearing and site prep for the basketball court and other features.

Pathway

 

gravel pad

 

UPDATE 10/24/25:

Construction has begun with crews clearing the old basketball hoop and other items slated for replacement.

machines clearing

clearing the park

Project Timeline

complete
complete

Community Input (Winter 2025)

complete
complete

Design Concept Review & Approval (Spring 2025)

live
live

Under Construction (Fall 2025-Summer 2026)

planned
planned

Completion & Ribbon Cutting (Summer 2026)